YEAR 12 · NETWORKS, SCHEDULING AND ASSIGNMENT

Topic review.

Connect the key ideas, then choose a practice paper.

01 / QUICK RECAP

Connect the ideas.

  • An activity's immediate predecessors must finish before it can start. An arrow shows the permitted direction; its duration is not its drawn length.
  • In an activity-on-arrow project network, numbered vertices are events. A dashed dummy arrow has zero duration and records a dependency.
  • A forward scan takes the largest incoming finish time. A backward scan takes the smallest permitted outgoing start time.
  • The critical path is a longest-duration start-to-finish path. There can be more than one, and shortening one activity need not shorten the project by the same amount.
  • Total float of an activity is latest head-event time minus earliest tail-event time minus its duration. All times use one stated unit.
  • An assignment selects exactly one entry in each relevant row and column. Row-by-row cheapest choices can conflict.
  • Row and column reductions preserve the optimal complete assignment. Independent zeros occupy different rows and columns.
  • To maximise profit, transform profits into opportunity losses; for a rectangular model, state the meaning and cost of any dummy assignment.
  • Report the chosen people, tasks, completion time or total cost, together with the assumptions under which the recommendation works.
02 / PRACTICE TESTS

Put it together.

Choose a paper and show your working.

  1. Networks, scheduling and assignment — Test 1

    A balanced first paper covering project scans, critical paths, assignment reductions and sensible recommendations.

    10 questions · 58 marks · 65 minutes · Scientific calculator
  2. Networks, scheduling and assignment — Test 2

    Develop scheduling calculations and compare minimum-cost, maximum-profit and rectangular assignments.

    10 questions · 59 marks · 65 minutes · Scientific calculator
  3. Networks, scheduling and assignment — Test 3

    Analyse multiple critical paths, constrained resources and assignments with unavailable or unfilled tasks.

    10 questions · 58 marks · 75 minutes · Scientific calculator
  4. Networks, scheduling and assignment — Test 4

    Use inverse scheduling and expediting decisions, then justify assignment reductions and interpret operational restrictions.

    10 questions · 54 marks · 75 minutes · Scientific calculator
  5. Networks, scheduling and assignment — Test 5

    Critique scheduling claims and test how deadlines, cost changes and ties affect recommendations.

    10 questions · 55 marks · 75 minutes · Scientific calculator
  6. Networks, scheduling and assignment — Test 6

    A more demanding applications paper combining network sensitivity, resource assumptions and assignment-model choices.

    10 questions · 60 marks · 75 minutes · Scientific calculator
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.