YEAR 12 · NETWORKS, SCHEDULING AND ASSIGNMENT · 20 MIN

Minimum completion time

Interpret the network's earliest finish as a lower bound under stated assumptions, and test how time reductions change that finish.

In this lesson

Before you start
  • Critical paths
  • Precedence tables
01 / LEARN

Understand the idea.

Minimum under a model

The forward scan gives the earliest completion under the stated dependencies and durations. It assumes every ready activity can obtain the resources it needs immediately. A single shared machine may prevent the parallel starts that this basic model allows.

The display tasks contain 4+3+5+4+2+3=21 days of activity time, but overlap permits a 13-day elapsed schedule. Total work and elapsed duration answer different questions; the network minimum is conditional on its timing and resource assumptions.

A school display project. Times are in days.
ActivityDurationImmediate predecessors
A4None
B3None
C5A
D4A
E2B and D
F3C and E

Shortening the project

To shorten completion, change a controlling activity or a dependency that can legitimately be changed, then rescan. The saving on an individual task need not equal the saving for the whole project: another path can become the longest.

Reducing D from 4 to 3 days makes A–D–E–F take 12 days, tying A–C–F. Further reductions to D alone leave A–C–F at 12, so they cannot reduce the overall finish below that limit.

02 / WORKED EXAMPLES

See the method in action.

EXAMPLE 01

Work versus elapsed time

Tasks A (5 hours) and B (8 hours) start together. C (2 hours) follows both. Find the total work and minimum elapsed duration, assuming independent resources.

Worked solution

  1. 1

    Add every activity to measure total work.

    W=5+8+2=15 task-hours

    Total work counts both parallel activities as well as the following activity.

  2. 2

    Find when C can start.

    ESC=max(5,8)=8 hours

    A and B start together, and C requires completion of both.

  3. 3

    Add the final sequential activity.

    T=8+2=10 hours

    Only C's two hours follow the parallel stage, so elapsed time is less than total work.

Answer

15 task-hours of work; 10 hours elapsed.

EXAMPLE 02

Check a proposed reduction

A project has path durations 18 and 16 days. A task only on the 18-day path can be shortened by 4 days. What is the new earliest completion?

Worked solution

  1. 1

    Reduce the affected route.

    18−4=14 days

    The shortened task occurs only on the original 18-day path.

  2. 2

    Retain the other route's duration.

    T2=16 days

    None of the changed work lies on this route.

  3. 3

    Recalculate project completion.

    T=max(14,16)=16 days

    The unchanged route becomes critical and prevents a 14-day project finish.

  4. 4

    Measure the overall saving.

    18−16=2 days

    Only two of the four task-days saved reduce elapsed project duration.

Answer

16 days: the four-day task reduction saves only two days overall.

03 / YOUR TURN

Try it yourself.

Check your understanding

The longest route is 30 days and the next longest is 28. A task appearing only on the longest is shortened by 5 days. What finish time results?

Show answer & reasoning

28 days.

The changed route takes 30−5=25 days, while the other remains at 28. Their maximum is 28 days, so the project saves two days rather than five.

Keep practising

6 worksheet questions · 16 marks

Read the questions online
  1. Find the display project's total activity duration and its earliest elapsed completion.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  2. Reduce D in the display project from 4 to 3 days. Find the new completion and all critical real-activity paths.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  3. Instead reduce D from 4 to 1 day. Find the new project completion.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  4. Two independent tasks each last 6 hours but need the same one available operator. A final 1-hour task follows both. Compare the dependency-only minimum with a schedule respecting the operator limit.
    3 marks
  5. A project has a 22-day critical path and a 21-day alternative. A one-day reduction is available on a task shared by both routes. What revised completion results?
    2 marks
  6. A contractor promises the exact network minimum with no allowance for uncertainty. Give two assumptions that should be checked.
    2 marks
Read the worked solutions

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Find the display project's total activity duration and its earliest elapsed completion.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    Sum 4+3+5+4+2+3=21.

    The controlling route A–D–E–F takes 13.

    21 task-days; 13 elapsed days.
  2. Reduce D in the display project from 4 to 3 days. Find the new completion and all critical real-activity paths.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    The changed D route is 4+3+2+3=12.

    The C route remains 4+5+3=12.

    12 days; A–D–E–F and A–C–F.
  3. Instead reduce D from 4 to 1 day. Find the new project completion.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    The D route becomes 4+1+2+3=10.

    The unchanged A–C–F route still needs 12.

    12 days.
  4. Two independent tasks each last 6 hours but need the same one available operator. A final 1-hour task follows both. Compare the dependency-only minimum with a schedule respecting the operator limit.
    3 marks

    Parallel model: max(6,6)+1=7.

    One operator must do the two tasks sequentially: 6+6+1=13.

    Dependency-only minimum 7 hours; with one operator, 13 hours.
  5. A project has a 22-day critical path and a 21-day alternative. A one-day reduction is available on a task shared by both routes. What revised completion results?
    2 marks

    Both path durations fall by one.

    They become 21 and 20; the maximum is 21.

    21 days.
  6. A contractor promises the exact network minimum with no allowance for uncertainty. Give two assumptions that should be checked.
    2 marks

    The calculation uses fixed durations and immediate starts.

    Supply delays, resource conflicts or rework can invalidate these assumptions.

    For example: the activity durations are reliable, and enough independent resources exist for parallel tasks.
Checking saved progress…
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.

Official curriculum source ↗