YEAR 12 · NETWORKS, SCHEDULING AND ASSIGNMENT · 18 MIN

Dummy activities

Use zero-duration dummy arrows to show dependencies correctly in an activity-on-arrow network.

In this lesson

Before you start
  • Directed project networks
  • Immediate predecessors
01 / LEARN

Understand the idea.

A dependency without work

A dummy activity is a zero-duration logical link, usually drawn as a dashed arrow. It adds no work or resource use, but it carries a completion requirement from one event to another. Removing it can therefore change which activities may start.

In the displayed network, C needs A only, while E needs B and D. Keeping separate events lets C begin after A; the dummy carries B into E's start event without making C wait for B.

Check both sides of the rule

Before adding a dummy, identify both the activities that must inherit the dependency and those that must remain independent. Afterwards, trace their start requirements again. A misplaced dummy can add an unwanted dependency or create a directed cycle.

Zero duration does not make the start event occur earlier. If a dummy comes from a late event, the event at its head must still wait for that completion. Include the dummy in forward and backward scans with duration zero.

02 / WORKED EXAMPLES

See the method in action.

EXAMPLE 01

A zero duration can still matter

A finishes at day 4. B finishes at day 7. A dummy from the end of B enters the event where C starts after A. C lasts 3 days. Find C's earliest finish.

Worked solution

  1. 1

    Carry B's finish through the dummy.

    7+0=7 days

    The dummy takes no additional time but cannot finish before B does.

  2. 2

    Find the earliest start of C.

    ESC=max(4,7)=7 days

    C's start event requires completion of A and the incoming dummy.

  3. 3

    Add C's own duration.

    EFC=7+3=10 days

    C needs three days after all its predecessors are ready.

Answer

C finishes earliest at day 10.

EXAMPLE 02

Keep one branch independent

A and B start together. C follows A only; D follows both A and B. Explain why making C and D leave one merged A/B finish event is incorrect.

Worked solution

  1. 1

    Interpret a merged A/B event.

    Every activity leaving that event must wait until both A and B have finished.

  2. 2

    Identify the unwanted condition on C.

    B→C

    C is supposed to follow A only, so requiring completion of B changes the stated project.

  3. 3

    Separate C's start from D's start.

    Let C leave A's finish event. Connect that event and B's finish to D's start, using a zero-duration dummy where needed, so D alone waits for both.

Answer

The merged event adds an unwanted B→C dependency. A dummy can record B→D without adding B→C.

03 / YOUR TURN

Try it yourself.

Check your understanding

In the displayed network, what would be lost if the dummy 3→4 were removed?

Show answer & reasoning

E would no longer be required to wait for B.

E would lose its requirement to wait for B. B finishes at event 3, and the dummy from event 3 to event 4 is the link carrying that completion to E's start event.

Keep practising

6 worksheet questions · 13 marks

Read the questions online
  1. For the displayed network, state the duration and purpose of the dashed arrow.
    2 marks
  2. A dummy joins an event reached at time 9 to an event otherwise ready at time 6. What is the earliest time of the receiving event?
    2 marks
  3. P and Q start together. R follows P only, S follows Q only, and T follows both P and Q. Explain why one joint event for the ends of P and Q can be unsuitable.
    3 marks
  4. A student gives a dummy a duration of 2 hours to represent administrative waiting. Is that still a dummy?
    2 marks
  5. Can a dummy have a direct financial cost in this scheduling model? Explain.
    2 marks
  6. A finishes at 5, B at 8, and C at 6. Task D requires all three and takes 4 days. Dummies are used to join the requirements. Find D's earliest finish.
    2 marks
Read the worked solutions

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. For the displayed network, state the duration and purpose of the dashed arrow.
    2 marks

    The arrow 3→4 is a logical connection.

    It records B's completion without adding a real task.

    Duration 0 days; it makes E wait for B as well as D.
  2. A dummy joins an event reached at time 9 to an event otherwise ready at time 6. What is the earliest time of the receiving event?
    2 marks

    The zero-duration dummy arrives at 9+0=9.

    Take max(6,9)=9.

    9.
  3. P and Q start together. R follows P only, S follows Q only, and T follows both P and Q. Explain why one joint event for the ends of P and Q can be unsuitable.
    3 marks

    R and S have different predecessor sets.

    Use separate finish events and logical dummy links to create T's joint requirement.

    It would force R to wait for Q and S to wait for P.
  4. A student gives a dummy a duration of 2 hours to represent administrative waiting. Is that still a dummy?
    2 marks

    A dummy has exactly zero duration.

    A genuine two-hour wait must be modelled as a real timed activity or lag.

    No.
  5. Can a dummy have a direct financial cost in this scheduling model? Explain.
    2 marks

    It represents a dependency only, not real work.

    Costs caused by the resulting schedule must be modelled separately.

    No direct task cost is assigned to a dummy.
  6. A finishes at 5, B at 8, and C at 6. Task D requires all three and takes 4 days. Dummies are used to join the requirements. Find D's earliest finish.
    2 marks

    Its starting event is max(5,8,6)=8.

    Finish time is 8+4=12.

    12 days.
Checking saved progress…
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.

Official curriculum source ↗

Save your next step.

Create a free account to save your learning progress. Lessons and downloads stay free, with or without an account.

Create free account