Assignment cost tables

Read an assignment table, enforce the one-person/one-job constraints and evaluate complete assignments using the original entries.

In this lesson

Before you start
  • Reading matrices
  • Adding costs
01 / LEARN

Understand the idea.

What the rows and columns mean

An assignment table records the value of pairing a row item with a column item. In a complete square assignment, each person does one job and each job receives one person, so selected entries must occupy distinct rows and columns.

Read the caption before calculating: cost is usually minimised, while profit is usually maximised. Check units and unavailable pairings. A forbidden pairing is excluded; giving it a zero would instead make it look particularly attractive in a cost problem.

Cost ($) of assigning one technician to each job.
TechnicianJob 1Job 2Job 3
Ali927
Bea643
Chen581

Whole assignments, not isolated bargains

Individual bargains can conflict. Choosing the cheapest entry in each row is valid only if the selected columns are distinct. For three people there are 3!=6 complete allocations, so every feasible total can be compared directly.

In the technician table, Ali→2, Bea→1 and Chen→3 costs 2+6+1=9 dollars. Bea's own cheapest job is 3, but assigning her there as well as Chen would leave job 1 uncovered.

02 / WORKED EXAMPLES

See the method in action.

EXAMPLE 01

Evaluate a complete allocation

Using the technician table, calculate the cost of Ali→3, Bea→2 and Chen→1.

Cost ($) of assigning one technician to each job.
TechnicianJob 1Job 2Job 3
Ali927
Bea643
Chen581

Worked solution

  1. 1

    Check that every job is used once.

    {3,2,1}={1,2,3}

    Ali, Bea and Chen receive different jobs, so this is a feasible complete assignment.

  2. 2

    Read the three original entries.

    cAli,3=7cBea,2=4cChen,1=5

    Each cost is found at the intersection of the named technician's row and assigned job's column.

  3. 3

    Add the selected costs.

    C=7+4+5=16 dollars

    The assignment objective is the sum of costs for these three pairings.

Answer

$16.

EXAMPLE 02

Reject an infeasible selection

A student chooses Ali→2, Bea→3 and Chen→3. Why is the proposed $6 total not a valid solution?

Worked solution

  1. 1

    Check the proposed arithmetic.

    2+3+1=6 dollars

    The entries have been added correctly, but a correct sum alone does not establish feasibility.

  2. 2

    Count how often each job is selected.

    Job 1:0Job 2:1Job 3:2

    Bea and Chen both select job 3, while nobody selects job 1.

  3. 3

    Reject the allocation as infeasible.

    The one-person-per-job rule is broken, so six dollars cannot be reported as the cost of an admissible complete assignment.

Answer

It violates the one-person-per-job constraint, so the $6 sum is not an admissible assignment cost.

03 / YOUR TURN

Try it yourself.

Check your understanding

For a four-person/four-job table, how many entries are selected in a complete feasible assignment?

Show answer & reasoning

Four: one per row and one per column.

Four entries are selected. Each of the four people supplies one pairing, and distinct job columns ensure that the four required jobs are all covered exactly once.

Keep practising

6 worksheet questions · 16 marks

Read the questions online
  1. Use the technician table to find the cost of Ali→1, Bea→2 and Chen→3.
    2 marks
    Cost ($) of assigning one technician to each job.
    TechnicianJob 1Job 2Job 3
    Ali927
    Bea643
    Chen581
  2. List all six possible job sequences for Ali, Bea and Chen.
    3 marks
  3. Evaluate all six technician assignments and identify the minimum.
    4 marks
    Cost ($) of assigning one technician to each job.
    TechnicianJob 1Job 2Job 3
    Ali927
    Bea643
    Chen581
  4. A table records the time each driver needs for a separate delivery. Explain one assumption needed before minimising the sum of the times.
    2 marks
  5. A proposed allocation uses one entry in each column but two entries in one row. Is it feasible for a standard one-to-one square assignment?
    2 marks
  6. If every selected cost in a four-person assignment is increased by $3, how much does the total increase, and does this change which complete assignment is cheapest?
    3 marks
Read the worked solutions

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Use the technician table to find the cost of Ali→1, Bea→2 and Chen→3.
    2 marks
    Cost ($) of assigning one technician to each job.
    TechnicianJob 1Job 2Job 3
    Ali927
    Bea643
    Chen581

    Read 9,4 and 1.

    9+4+1=14.

    $14.
  2. List all six possible job sequences for Ali, Bea and Chen.
    3 marks

    Choose one of three jobs for Ali, then one of the remaining two for Bea.

    Chen receives the remaining job.

    (1,2,3), (1,3,2), (2,1,3), (2,3,1), (3,1,2), (3,2,1).
  3. Evaluate all six technician assignments and identify the minimum.
    4 marks
    Cost ($) of assigning one technician to each job.
    TechnicianJob 1Job 2Job 3
    Ali927
    Bea643
    Chen581

    Use the six sequences from the preceding question.

    Add the three original entries for each sequence.

    The smallest total is 9.

    Totals $14, $20, $9, $10, $21, $16 respectively; minimum $9 with Ali→2, Bea→1, Chen→3.
  4. A table records the time each driver needs for a separate delivery. Explain one assumption needed before minimising the sum of the times.
    2 marks

    The sum and the maximum are different objective functions.

    The correct model must match the operational goal.

    For example, the objective really is total driver-hours, not the time when the last simultaneous delivery finishes.
  5. A proposed allocation uses one entry in each column but two entries in one row. Is it feasible for a standard one-to-one square assignment?
    2 marks

    One person would be assigned two jobs.

    Another row/person would necessarily be unassigned.

    No.
  6. If every selected cost in a four-person assignment is increased by $3, how much does the total increase, and does this change which complete assignment is cheapest?
    3 marks

    Each complete assignment contains four entries.

    Every possible total gains the same 4×3=$12.

    The total increases by $12; the ranking of complete assignments is unchanged.
Checking saved progress…
Curriculum reference & lesson scope

SACE Board of South Australia

Stage 2 General Mathematics: discrete models, project scheduling and assignment. Activity-on-arrow conventions are used for project networks; technology may verify calculations but does not replace interpreting the model.

Official curriculum source ↗

Save your next step.

Create a free account to save your learning progress. Lessons and downloads stay free, with or without an account.

Create free account