Year 12 General Mathematics math worksheets
Year 12 General Mathematics Minimum completion time Worksheet
Read the worksheet online
minimum completion time
- Find the display project's total activity duration and its earliest elapsed completion.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E - Reduce D in the display project from 4 to 3 days. Find the new completion and all critical real-activity paths.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E - Instead reduce D from 4 to 1 day. Find the new project completion.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E - Two independent tasks each last 6 hours but need the same one available operator. A final 1-hour task follows both. Compare the dependency-only minimum with a schedule respecting the operator limit.3 marks
- A project has a 22-day critical path and a 21-day alternative. A one-day reduction is available on a task shared by both routes. What revised completion results?2 marks
- A contractor promises the exact network minimum with no allowance for uncertainty. Give two assumptions that should be checked.2 marks