Year 12 General Mathematics math worksheet answers
Year 12 General Mathematics Minimum completion time Worksheet Answers
Read the answers online
minimum completion time
Equivalent correct methods earn the corresponding marks. Include units where asked.
- Find the display project's total activity duration and its earliest elapsed completion.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E Sum .
The controlling route A–D–E–F takes 13.
21 task-days; 13 elapsed days. - Reduce D in the display project from 4 to 3 days. Find the new completion and all critical real-activity paths.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E The changed D route is .
The C route remains .
12 days; A–D–E–F and A–C–F. - Instead reduce D from 4 to 1 day. Find the new project completion.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E The D route becomes .
The unchanged A–C–F route still needs 12.
12 days. - Two independent tasks each last 6 hours but need the same one available operator. A final 1-hour task follows both. Compare the dependency-only minimum with a schedule respecting the operator limit.3 marks
Parallel model: .
One operator must do the two tasks sequentially: .
Dependency-only minimum 7 hours; with one operator, 13 hours. - A project has a 22-day critical path and a 21-day alternative. A one-day reduction is available on a task shared by both routes. What revised completion results?2 marks
Both path durations fall by one.
They become 21 and 20; the maximum is 21.
21 days. - A contractor promises the exact network minimum with no allowance for uncertainty. Give two assumptions that should be checked.2 marks
The calculation uses fixed durations and immediate starts.
Supply delays, resource conflicts or rework can invalidate these assumptions.
For example: the activity durations are reliable, and enough independent resources exist for parallel tasks.
