minimum completion time

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Find the display project's total activity duration and its earliest elapsed completion.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    Sum 4+3+5+4+2+3=21.

    The controlling route A–D–E–F takes 13.

    21 task-days; 13 elapsed days.
  2. Reduce D in the display project from 4 to 3 days. Find the new completion and all critical real-activity paths.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    The changed D route is 4+3+2+3=12.

    The C route remains 4+5+3=12.

    12 days; A–D–E–F and A–C–F.
  3. Instead reduce D from 4 to 1 day. Find the new project completion.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    The D route becomes 4+1+2+3=10.

    The unchanged A–C–F route still needs 12.

    12 days.
  4. Two independent tasks each last 6 hours but need the same one available operator. A final 1-hour task follows both. Compare the dependency-only minimum with a schedule respecting the operator limit.
    3 marks

    Parallel model: max(6,6)+1=7.

    One operator must do the two tasks sequentially: 6+6+1=13.

    Dependency-only minimum 7 hours; with one operator, 13 hours.
  5. A project has a 22-day critical path and a 21-day alternative. A one-day reduction is available on a task shared by both routes. What revised completion results?
    2 marks

    Both path durations fall by one.

    They become 21 and 20; the maximum is 21.

    21 days.
  6. A contractor promises the exact network minimum with no allowance for uncertainty. Give two assumptions that should be checked.
    2 marks

    The calculation uses fixed durations and immediate starts.

    Supply delays, resource conflicts or rework can invalidate these assumptions.

    For example: the activity durations are reliable, and enough independent resources exist for parallel tasks.