- Calculate the total floats of B and C in the display project.3 marks
- Increase B's duration in the display project from 3 to 7 days. Find the project finish.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E - Increase B's duration instead to 9 days. Find the finish and critical real-activity sequence.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E - Activity P has , , and . Find its duration and float.2 marks
- A non-critical route takes 12 hours and the project finishes in 16. Two consecutive tasks on that route are both extended by 3 hours. What happens?3 marks
- The project deadline is fixed at day 20, but its earliest completion is day 18. Explain why a backward scan using 20 answers a different question from one using 18.3 marks