Year 12 General Mathematics Slack and changes to activities Worksheet

Open the PDF above, or read the online version below.

Read the worksheet online

slack and changes to activities

  1. Calculate the total floats of B and C in the display project.
    3 marks
  2. Increase B's duration in the display project from 3 to 7 days. Find the project finish.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  3. Increase B's duration instead to 9 days. Find the finish and critical real-activity sequence.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E
  4. Activity P has ES=6, EF=10, LS=9 and LF=13. Find its duration and float.
    2 marks
  5. A non-critical route takes 12 hours and the project finishes in 16. Two consecutive tasks on that route are both extended by 3 hours. What happens?
    3 marks
  6. The project deadline is fixed at day 20, but its earliest completion is day 18. Explain why a backward scan using 20 answers a different question from one using 18.
    3 marks