Year 12 General Mathematics math worksheet answers
Year 12 General Mathematics Slack and changes to activities Worksheet Answers
Read the answers online
slack and changes to activities
Equivalent correct methods earn the corresponding marks. Include units where asked.
- Calculate the total floats of B and C in the display project.3 marks
B: .
C: .
B: 5 days; C: 1 day. - Increase B's duration in the display project from 3 to 7 days. Find the project finish.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E E waits for .
E finishes 10 and F finishes 13.
13 days. - Increase B's duration instead to 9 days. Find the finish and critical real-activity sequence.3 marks
A school display project. Times are in days. Activity Duration Immediate predecessors A 4 None B 3 None C 5 A D 4 A E 2 B and D F 3 C and E E starts at .
It finishes 11; F finishes 14.
The B branch now controls.
14 days; B–E–F. - Activity P has , , and . Find its duration and float.2 marks
(also ).
.
Duration 4; float 3 time units. - A non-critical route takes 12 hours and the project finishes in 16. Two consecutive tasks on that route are both extended by 3 hours. What happens?3 marks
Its shared allowance was .
The combined extension is 6, so it exceeds the allowance by 2.
That route becomes 18 hours, delaying the project by 2 hours. - The project deadline is fixed at day 20, but its earliest completion is day 18. Explain why a backward scan using 20 answers a different question from one using 18.3 marks
A looser finish target creates two days of overall schedule allowance.
State the finish target before interpreting zero or positive float.
The day-20 scan finds latest times that meet the deadline; the day-18 scan finds float that preserves the earliest completion.
