slack and changes to activities

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Calculate the total floats of B and C in the display project.
    3 marks

    B: 8−0−3=5.

    C: 10−4−5=1.

    B: 5 days; C: 1 day.
  2. Increase B's duration in the display project from 3 to 7 days. Find the project finish.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    E waits for max(B finish 7,D finish 8)=8.

    E finishes 10 and F finishes 13.

    13 days.
  3. Increase B's duration instead to 9 days. Find the finish and critical real-activity sequence.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    E starts at max(9,8)=9.

    It finishes 11; F finishes 14.

    The B branch now controls.

    14 days; B–E–F.
  4. Activity P has ES=6, EF=10, LS=9 and LF=13. Find its duration and float.
    2 marks

    Duration=10−6=4 (also 13−9=4).

    Float=9−6=3.

    Duration 4; float 3 time units.
  5. A non-critical route takes 12 hours and the project finishes in 16. Two consecutive tasks on that route are both extended by 3 hours. What happens?
    3 marks

    Its shared allowance was 16−12=4.

    The combined extension is 6, so it exceeds the allowance by 2.

    That route becomes 18 hours, delaying the project by 2 hours.
  6. The project deadline is fixed at day 20, but its earliest completion is day 18. Explain why a backward scan using 20 answers a different question from one using 18.
    3 marks

    A looser finish target creates two days of overall schedule allowance.

    State the finish target before interpreting zero or positive float.

    The day-20 scan finds latest times that meet the deadline; the day-18 scan finds float that preserves the earliest completion.