- In the displayed network, give the start and finish event numbers for D.1 mark
- In the displayed network, which labelled real activities may start directly at event 1?2 marks
- A network has A: 1→2, B: 1→3 and C: 2→4. Does C require B to finish? Explain.2 marks
- A project diagram uses arrow lengths 3 cm and 8 cm for tasks of 9 days and 2 days. Is the drawing necessarily wrong?2 marks
- List the real activity sequences along the displayed start-to-finish paths, ignoring the dummy as a real task.3 marks
- Describe one check that detects an accidental extra dependency in a project network.2 marks