Year 12 General Mathematics math worksheet answers
Year 12 General Mathematics Directed project networks Worksheet Answers
Read the answers online
directed project networks
Equivalent correct methods earn the corresponding marks. Include units where asked.
- In the displayed network, give the start and finish event numbers for D.1 mark
Read the tail and head of the arrow labelled D: 4.
D runs from event 2 to event 4. - In the displayed network, which labelled real activities may start directly at event 1?2 marks
Their arrows leave the project start.
A dummy is not needed for either starting task.
A and B. - A network has A: 1→2, B: 1→3 and C: 2→4. Does C require B to finish? Explain.2 marks
There is no dependency path from event 3 to event 2.
C requires the incoming work at event 2, which is A.
No. - A project diagram uses arrow lengths 3 cm and 8 cm for tasks of 9 days and 2 days. Is the drawing necessarily wrong?2 marks
Activity durations are read from their numerical labels.
Project networks are dependency diagrams, not scaled time lines.
No; arrow length does not encode duration unless a scale is explicitly stated. - List the real activity sequences along the displayed start-to-finish paths, ignoring the dummy as a real task.3 marks
Trace each directed route from event 1 to event 6.
The B route reaches event 4 through the zero-duration dummy.
A–C–F; A–D–E–F; B–E–F through the dummy connection. - Describe one check that detects an accidental extra dependency in a project network.2 marks
A valid drawing must include every stated requirement.
It must not force an activity to wait for an unrelated branch.
Compare the incoming requirements at each activity's start with its immediate predecessors in the table.