Year 12 General Mathematics math worksheets
Year 12 General Mathematics Critical paths Worksheet
Read the worksheet online
critical paths
- Find the critical path and its duration for the displayed network.3 marks
- Complete paths have durations 9, 15, 12 and 15 weeks. Find the completion time and number of critical paths.2 marks
- A project starts with P (3 hours) and Q (5 hours) in parallel. R (4 hours) follows P and S (2 hours) follows Q. T (1 hour) follows both R and S. Find all critical paths.3 marks
- A path contains a zero-duration dummy. Can it still be critical?2 marks
- A network shows three connected zero-float activities beginning at the project start but not reaching the finish. Is that list enough to name a complete critical path?2 marks
- The critical path has duration 24 hours. A non-critical path takes 21. If an activity appearing only on the non-critical path is extended by 4 hours, what is the revised completion time?3 marks