critical paths
Equivalent correct methods earn the corresponding marks. Include units where asked.
- Find the critical path and its duration for the displayed network.3 marks
; ; .
The maximum is 13.
A–D–E–F, 13 days. - Complete paths have durations 9, 15, 12 and 15 weeks. Find the completion time and number of critical paths.2 marks
Take the largest complete-path duration.
Both 15-week routes are controlling.
15 weeks and two critical paths. - A project starts with P (3 hours) and Q (5 hours) in parallel. R (4 hours) follows P and S (2 hours) follows Q. T (1 hour) follows both R and S. Find all critical paths.3 marks
.
.
P–R–T and Q–S–T, both 8 hours. - A path contains a zero-duration dummy. Can it still be critical?2 marks
A critical route is determined by total duration and dependency structure.
A dummy may be needed to connect that controlling route.
Yes. - A network shows three connected zero-float activities beginning at the project start but not reaching the finish. Is that list enough to name a complete critical path?2 marks
A critical path must run continuously from the start event to the finish event.
Continue tracing the controlling arrows.
No. - The critical path has duration 24 hours. A non-critical path takes 21. If an activity appearing only on the non-critical path is extended by 4 hours, what is the revised completion time?3 marks
The changed path becomes .
The new maximum is , so the critical path changes.
25 hours.