ASCENTLEARNING
Join a weekly class
Year 12 General Mathematics math worksheet answers

Year 12 General Mathematics Critical paths Worksheet Answers

Open the PDF above, or read the online version below.

Read the answers online

critical paths

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Find the critical path and its duration for the displayed network.
    3 marks

    A–C–F=12; A–D–E–F=13; B–dummy–E–F=8.

    The maximum is 13.

    A–D–E–F, 13 days.
  2. Complete paths have durations 9, 15, 12 and 15 weeks. Find the completion time and number of critical paths.
    2 marks

    Take the largest complete-path duration.

    Both 15-week routes are controlling.

    15 weeks and two critical paths.
  3. A project starts with P (3 hours) and Q (5 hours) in parallel. R (4 hours) follows P and S (2 hours) follows Q. T (1 hour) follows both R and S. Find all critical paths.
    3 marks

    3+4+1=8.

    5+2+1=8.

    P–R–T and Q–S–T, both 8 hours.
  4. A path contains a zero-duration dummy. Can it still be critical?
    2 marks

    A critical route is determined by total duration and dependency structure.

    A dummy may be needed to connect that controlling route.

    Yes.
  5. A network shows three connected zero-float activities beginning at the project start but not reaching the finish. Is that list enough to name a complete critical path?
    2 marks

    A critical path must run continuously from the start event to the finish event.

    Continue tracing the controlling arrows.

    No.
  6. The critical path has duration 24 hours. A non-critical path takes 21. If an activity appearing only on the non-critical path is extended by 4 hours, what is the revised completion time?
    3 marks

    The changed path becomes 21+4=25.

    The new maximum is max(24,25)=25, so the critical path changes.

    25 hours.