Year 12 General Mathematics Dummy activities Worksheet Answers

Open the PDF above, or read the online version below.

Read the answers online

dummy activities

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. For the displayed network, state the duration and purpose of the dashed arrow.
    2 marks

    The arrow 3→4 is a logical connection.

    It records B's completion without adding a real task.

    Duration 0 days; it makes E wait for B as well as D.
  2. A dummy joins an event reached at time 9 to an event otherwise ready at time 6. What is the earliest time of the receiving event?
    2 marks

    The zero-duration dummy arrives at 9+0=9.

    Take max(6,9)=9.

    9.
  3. P and Q start together. R follows P only, S follows Q only, and T follows both P and Q. Explain why one joint event for the ends of P and Q can be unsuitable.
    3 marks

    R and S have different predecessor sets.

    Use separate finish events and logical dummy links to create T's joint requirement.

    It would force R to wait for Q and S to wait for P.
  4. A student gives a dummy a duration of 2 hours to represent administrative waiting. Is that still a dummy?
    2 marks

    A dummy has exactly zero duration.

    A genuine two-hour wait must be modelled as a real timed activity or lag.

    No.
  5. Can a dummy have a direct financial cost in this scheduling model? Explain.
    2 marks

    It represents a dependency only, not real work.

    Costs caused by the resulting schedule must be modelled separately.

    No direct task cost is assigned to a dummy.
  6. A finishes at 5, B at 8, and C at 6. Task D requires all three and takes 4 days. Dummies are used to join the requirements. Find D's earliest finish.
    2 marks

    Its starting event is max(5,8,6)=8.

    Finish time is 8+4=12.

    12 days.