Year 12 General Mathematics Precedence tables Worksheet Answers

Open the PDF above, or read the online version below.

Read the answers online

Precedence tables

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Using the display-project table, identify every activity that can start at time 0.
    2 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    A and B have 'None' in the predecessor column.

    All other activities require at least one earlier activity.

    A and B.
  2. Using the display-project table, state the immediate predecessors and all indirect predecessors of F.
    3 marks
    A school display project. Times are in days.
    ActivityDurationImmediate predecessors
    A4None
    B3None
    C5A
    D4A
    E2B and D
    F3C and E

    F needs C and E.

    C needs A; E needs B and D; D needs A.

    A, B and D are earlier requirements but not immediate predecessors of F.

    Immediate: C and E. Indirect: A, B and D.
  3. A delivery A takes 1 day. Cutting B and cleaning C each follow A. Fitting D needs both B and C. Write just the predecessor column for A, B, C and D.
    3 marks

    B and C each depend directly on delivery.

    D needs both branches to finish.

    A: none; B: A; C: A; D: B and C.
  4. A table says A follows C, B follows A, and C follows B. Explain why this is not a workable project plan.
    2 marks

    A waits for C, C waits for B, and B waits for A.

    There is no starting activity to break the cycle.

    It contains the cycle A → B → C → A, so no activity can begin.
  5. Painting P follows priming R, which follows cleaning C. Should the immediate predecessors of P be C and R? Explain.
    2 marks

    Cleaning is already required before priming.

    Completing R therefore guarantees completion of C.

    No; list R only.
  6. Two independent jobs have no predecessors, but both need the same single crane. Does the precedence table alone guarantee that they can occur together?
    2 marks

    Logical independence allows parallel scheduling in the basic model.

    A shared crane is a resource constraint that must be modelled or scheduled separately.

    No.