forward and backward scans

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. Perform a complete forward scan on the displayed network.
    4 marks

    E1=0; E2=4; E3=3.

    E4=max(4+4,3+0)=8.

    E5=max(4+5,8+2)=10; E6=10+3=13.

    Events 1–6: 0, 4, 3, 8, 10, 13.
  2. Perform the backward scan for the displayed network using project finish 13.
    4 marks

    L6=13; L5=10; L4=8; L3=8.

    L2=min(10−5,8−4)=4.

    L1=min(4−4,8−3)=0.

    Events 1–6 latest: 0, 4, 8, 8, 10, 13.
  3. Find the earliest time at a merge when incoming tail times and durations are (2,7), (6,2) and (4,6).
    2 marks

    Candidates are 9, 8 and 10.

    Their maximum is 10.

    10.
  4. Find a latest event time when outgoing head times and durations are (15,4), (19,6) and (14,2).
    2 marks

    Candidates are 11, 13 and 12.

    Their minimum is 11.

    11.
  5. A forward scan gives an event earliest time 9. A claimed backward scan gives latest time 7 for a finish target equal to the earliest project finish. What does this indicate?
    2 marks

    The event cannot both require at least 9 and be required by 7.

    Recheck durations, directions and the final-time assumption.

    The scans or the model contain an error.
  6. Why does adding all incoming durations at a merge usually give the wrong earliest time?
    2 marks

    Each candidate already measures elapsed time from the common start.

    The event waits for the latest arrival, not the sum of arrivals.

    It assumes parallel branches occurred one after another.