Year 12 General Mathematics math worksheet answers
Year 12 General Mathematics Earliest/latest times Worksheet Answers
Read the answers online
earliest/latest times
Equivalent correct methods earn the corresponding marks. Include units where asked.
- Use the display project to find , , and for B.3 marks
Forward and backward scans for the display network, with completion at day 13. Event Earliest time Latest time 1 0 0 2 4 4 3 3 8 4 8 8 5 10 10 6 13 13 B is 1→3 of duration 3.
; ; ; .
0, 3, 5 and 8 days respectively. - Find all four activity times for C in the display project.3 marks
Forward and backward scans for the display network, with completion at day 13. Event Earliest time Latest time 1 0 0 2 4 4 3 3 8 4 8 8 5 10 10 6 13 13 C is 2→5 of duration 5.
; ; ; .
, , , days. - Find all four times for E in the display project.2 marks
Forward and backward scans for the display network, with completion at day 13. Event Earliest time Latest time 1 0 0 2 4 4 3 3 8 4 8 8 5 10 10 6 13 13 E is 4→5 of duration 2.
Use and .
, , , days. - A task lasts 8 minutes. Its is 12 and is 15. Find and .2 marks
Add the same fixed duration to each start.
; .
and minutes. - An activity runs 2→5 for 3 days. , and . Find its earliest finish and explain why it differs from .3 marks
The task itself finishes at .
An event combines all incoming requirements.
days; event 5 waits for another incoming activity until day 12. - A claimed schedule gives , , and for one fixed-duration activity. Identify the inconsistency.2 marks
.
; the same activity cannot have both durations in this model.
The duration would be 6 from / but 5 from /.