Year 12 General Mathematics Checking assumptions and interpreting recommendations Worksheet Answers

Open the PDF above, or read the online version below.

Read the answers online

checking assumptions and interpreting recommendations

Equivalent correct methods earn the corresponding marks. Include units where asked.

  1. The technician minimum is $9. Write a recommendation that includes the pairings and one assumption.
    3 marks
    Cost ($) of assigning one technician to each job.
    TechnicianJob 1Job 2Job 3
    Ali927
    Bea643
    Chen581

    Identify the chosen entries, not only the total.

    State a relevant feasibility/additivity assumption.

    Assign Ali to 2, Bea to 1 and Chen to 3 for $9, assuming all are available and each does exactly one independent job.
  2. Ali cannot do job 2. Find and interpret the new technician optimum.
    3 marks
    Cost ($) of assigning one technician to each job.
    TechnicianJob 1Job 2Job 3
    Ali927
    Bea643
    Chen581

    Exclude the two assignments using Ali→2.

    Among the remaining totals 14,20,21,16, choose 14.

    $14: Ali→1, Bea→2, Chen→3.
  3. Why is $1,000 a safe substitute for the forbidden entry in the preceding problem when all other costs are nonnegative and a feasible $14 allocation is known?
    3 marks

    The bound depends on nonnegative remaining costs.

    The large value is justified by an actual feasible alternative.

    Any assignment using the forbidden entry would cost at least $1,000, so it cannot beat the feasible $14 assignment.
  4. A manager asks for the 'best assignment' but supplies both times and profits. What must be clarified before optimisation?
    2 marks

    Different objectives can select different pairings.

    A single optimisation requires an explicit criterion.

    The objective and any constraints: for example minimise total time, maximise profit, or meet a time limit then maximise profit.
  5. A project finish moves from 20 to 21 days when an uncertain activity is extended by 3 days. What does this tell you?
    3 marks

    The delay in the overall finish is only 1 day.

    Not every task-duration change transfers fully to project duration.

    The network absorbed two days of that change before it affected the finish, but the revised critical structure must still be checked.
  6. An optimal assignment leaves one job with a dummy worker. Write the limitation that must accompany the recommendation.
    2 marks

    Identify the uncompleted job explicitly.

    If every job is mandatory, the original capacity model must be revised.

    That real job remains unfilled, with the stated penalty or allowed omission; the model has not created an extra worker.